VTC · Insulation Procurement

Operations & KPI Hub

Weekly Operations
DEPARTMENT PLAYBOOK & OPERATING SYSTEM

Insulation Procurement Objectives & Weekly Execution

A visual roadmap connecting our 6 Core KPIs, their underlying Data Sources, and the Daily & Weekly Routines that prevent shortages, eliminate past-due orders, and keep production moving.

6 Core Department KPIs Zero-delay mindset
6 System Data Feeds QTO · OOR · Medius · QCBD
8 Weekly Sync Meetings Suppliers & Hotlist
2 Daily Execution Blocks 1st Half vs. 2nd Half
PART 1A · PERFORMANCE METRICS & ORIGINS

Department KPIs & Where They Feed From

Click any Data Source below to highlight the exact KPIs and sub-metrics it powers.

1. SOURCE REPORTS & PLATFORMS
MRP / QTO Report Open.pur.ven (OOR) Buyer Dashboard Medius System Hotlist Tracker QCBD System
2. ACTIVE BUYER ROUTINES
Weekly Backlog Placement Oldest-to-Newest Past Due Scrub Daily Hotlist & EPPM Mitigation
3. DEPARTMENT KPI TARGETS
0 EPPMs 100% Confirmed & Updated Dates 0 Unresolved Past Dues
KPI 01
QTO Report Open Order

No EPPMs

Preventing material shortages & production delays across all divisions

1a Zero POs Not Placed Out of Lead Time
↳ Fed by: QTO Report
1b Late POs Reschedule
↳ Fed by: Open Order
KPI 02
Manual from Dashboard

Order Confirmation

Ensuring every issued PO is acknowledged & confirmed by the supplier

Data Origin Manual extraction & tracking from Buyer Dashboard
Objective 100% supplier acknowledgment & verified delivery commitment
KPI 03
Open Order

Past Due Review

Active scrubbing of open purchase orders sorted oldest to newest

3a Updated Ship Dates (and No Past Due)
↳ Fed by: Open Order (Open.pur.ven)
KPI 04
Medius

Past Due Invoices

Preventing credit holds and resolving price/quantity discrepancies

Data Origin Medius AP Invoice Workflow System
Cadence Monitored at least every other day + daily 2nd Half block
KPI 05
Manual from Hotlist

Hotlist

Critical expedite tracking for urgent & delay-risk insulation items

Data Origin Manual from Hotlist (escalated from EPPM & plant priorities)
Cadence Updated daily + reviewed in Tue & Fri 10:00 AM Hotlist Meetings
KPI 06
Manual (QCBD)

NCRs

Non-Conformance Reports, Process Deviations (PDs) & Debit Memos

Data Origin Manual tracking via QCBD (assigned NCRs & open PDs)
Objective Timely disposition, PD approval follow-up & supplier recovery
PART 1B · STANDARD OPERATING PROCEDURES

6 Core Daily & Weekly Department Tasks

Standardized execution workflow for every Insulation Buyer — what to run, when to review, and how to act.

Daily Every Other Day 2–3x / Week Start of Week
01 Beginning of Each Week

MRP / QTO — Quantity to Order Report

“Backlog Report” (Bolton) · Feeds KPI #1

Run at the start of each week to keep tight focus on all backlog items that need Purchase Orders placed within lead time.

Run QTO (Bolton)
→
Prioritize Backlog
→
Place POs in Lead Time
02 A Couple Times a Week

EPPM — Insulation Materials (All Divisions)

Identifying Delay Report · Feeds KPI #1 & #5

Review across all divisions to spot potential material delays early. Once a delay is identified, work to improve delivery or qualify another source.

Spot Delay
→
Improve / Alt Source
→
If No Fix → Add to Hotlist
03 Daily Review

Hotlist Management

Critical Shortage & Expedite Tracker · Feeds KPI #5

Daily review must be completed for all your assigned items to capture tracking numbers, revised ship dates, and supplier status updates.

Check Assigned Items
→
Expedite Supplier
→
Log Daily Update
04 A Couple Times a Week

NCRs (QCBD) & Process Deviations

Quality Non-Conformances & PDs · Feeds KPI #6
  • a. Assigned NCRs: Monitor what has been assigned to you in QCBD a couple times a week.
  • b. Open PDs: If there are open Process Deviations (PDs), actively monitor them to secure engineering/quality approvals.
Check QCBD Queue
→
Chase PD Approvals
→
Close / Debit Memo
05 At Least Every Other Day

Invoices (Medius)

AP Invoice Resolution · Feeds KPI #4

Monitor your Medius queue at least every other day (and during the afternoon execution block) to clear price/receipt mismatches and prevent past-due invoices.

Open Medius Queue
→
Verify PO vs. Invoice
→
Approve / Resolve Hold
06 A Couple Times a Week

Open.pur.ven — Open Order Report (OOR)

Past Due & Reschedule Scrub · Feeds KPI #1b & #3

Filter by your Buyer Code and sort Delivery Date from Oldest to Newest. Review all past due orders to ensure they are received or resolved.

Filter Buyer Code
→
Sort Oldest → Newest
→
Receive or Update Date
PART 1C · WEEKLY CADENCE & SUPPLIER SYNCS

Monday – Friday Operating Schedule

Every day is structured into two focused halves: 1st Half (Communications, Supplier Meetings, Hotlist/QTO/EPPM) and 2nd Half (Projects, OOR & Medius).

MON

Monday

Kickoff & Scrub
☀️ 1st Half (Morning)
  • Emails
  • EPPM / Hotlist Updates
  • NCR’s / PD’s / Debit Memo’s
⚡ 2nd Half (Afternoon)
  • Projects
  • OOR (Open Order Report)
  • Medius (Invoices)
TUE

Tuesday

Weidmann & QTO
☀️ 1st Half (Morning)
  • Emails
  • 9:30 AM Weekly Weidmann Meeting
  • 10:00 AM Hotlist Meeting
  • QTO Report / PD’s / IC’s
  • Hotlist Updates
⚡ 2nd Half (Afternoon)
  • Projects
  • OOR (Open Order Report)
  • Medius (Invoices)
WED

Wednesday

Canduct & Shortages
☀️ 1st Half (Morning)
  • Emails
  • 10:00 AM Weekly Canduct Meeting
  • Hotlist Updates
  • Insulation Tracking Report (Components)
  • Short Report (Raw Material)
  • Projects
⚡ 2nd Half (Afternoon)
  • Projects
  • OOR (Open Order Report)
  • Medius (Invoices)
THU

Thursday

Transvick & Liaoning
☀️ 1st Half (Morning)
  • 8:30 AM Weekly Transvick Meeting
  • 10:00 AM Weekly Liaoning Meeting
  • Emails
  • EPPM / Hotlist Updates
  • NCR’s / PD’s / Debit Memo’s
⚡ 2nd Half (Afternoon)
  • Projects
  • OOR (Open Order Report)
  • Medius (Invoices)
FRI

Friday

Hitachi, Rochling & Closeout
☀️ 1st Half (Morning)
  • 8:00 AM Weekly Hitachi Meeting
  • 9:00 AM Weekly Rochling Meeting
  • Emails
  • 10:00 AM Hotlist Meeting
  • QTO Report / PD’s / IC’s
  • Hotlist Updates
⚡ 2nd Half (Afternoon)
  • Projects
  • OOR (Open Order Report)
  • Medius (Invoices)
SECTION 02 · IN DEVELOPMENT

Interactive KPIs Dashboard — Work in Progress

This module is currently being configured to track, calculate, and visualize real-time and manual department performance across all 6 Insulation Procurement KPIs.

KPI 01 Pending Data Feed

No EPPMs

Zero POs Out of Lead Time (QTO Report) & Late POs Reschedule (Open Order)

KPI 02 Pending Input Setup

Order Confirmation

Manual tracking from Buyer Dashboard

KPI 03 Pending Data Feed

Past Due Review

Updated Ship Dates & Zero Past Due (Open Order Report)

KPI 04 Pending Data Feed

Past Due Invoices

Medius AP workflow monitoring

KPI 05 Pending Input Setup

Hotlist

Manual from Hotlist tracker

KPI 06 Pending Input Setup

NCRs

Manual tracking from QCBD & Process Deviations (PDs)